Installation, made simple.
A clear overview of how Jarvalo systems go together. Always follow the printed guide for your product and local building rules.
Fluted panel 219 × 26
Batten 40 × 30
L-trim 50 × 50
Wall cladding
- Step 1
Check the wall
Sound, flat and weatherproof. Plan the ventilated gap and where openings fall.
- Step 2
Fix the battens
40 × 30 composite battens (XK-JO) at about 400 mm centres, square to the boards, plus one beside every opening. Anchor with 6 × 80 hammer-in fixings (XK-EXB).
- Step 3
Fit starter clips
One stainless starter clip (XK-SC) at the foot of each batten. They set the first row dead level.
- Step 4
Clip the panels
Seat each panel on the row below and fix one stainless cladding clip (XK-WC) per board at every batten.
- Step 5
Stagger the joints
Every board end lands on a batten. Offset joints between rows and leave the end gap for expansion.
- Step 6
Finish the edges
Close corners and board ends with 50 × 50 L-trims: XK-TD-ET for Classic, XK-CT-ET for Capped.
Decking
- Step 1
Prepare the base
A firm, free-draining slab or frame with a slight fall away from the house.
- Step 2
Lay the joists
Composite joists (XK-JO) at about 350 mm centres, or as the printed guide for your board says. Fix to concrete with hammer-in fixings.
- Step 3
Start at the edge
Hold the first board with starter clips (XK-SC).
- Step 4
Clip every board
Hidden clips in the board grooves: plastic XK-PC for a 6 mm gap or stainless XK-MC for 4 mm. Allow about 21 per m².
Official PDF guides will be published in Technical Resources once issued.